PROJECT information

Location: Dorval 
  
Duration of construction: 30 weeks of production and 64 days of installation 
  
Owner:Aéroport de Montréal 
  
Architect: Lemay et Associés 
  
Engineer: Nicolet Chartrand Knoll 
  
contractor: Aéroport de Montréal (ADM) 
  
Prefabricated components: 3 levels above ground including: 
 ● 75 columns 
 ● 192 internal beams 
 ● 66 bracing walls for 23 624 square feet 
 ● 696 double T for 336 558 square feet
 ● 64 exterior spandrels for 19 141 square feet

Location: Dorval 
  
Duration of construction: 30 weeks of production and 64 days of installation 
  
Owner:Aéroport de Montréal 
  
Architect: Lemay et Associés 
  
Engineer: Nicolet Chartrand Knoll 
  
contractor: Aéroport de Montréal (ADM) 
  
Prefabricated components: 3 levels above ground including: 
 ● 75 columns 
 ● 192 internal beams 
 ● 66 bracing walls for 23 624 square feet 
 ● 696 double T for 336 558 square feet
 ● 64 exterior spandrels for 19 141 square feet

DESCRIPTION

In the midst of the airport frenzy, it was necessary to optimize the parking space to its maximum which was achieved with spans of more than 60 feet reducing the number of columns and making the whole safer to circulate. The limitation of construction effects on the daily life of the airport was also a prerequisite.

In the midst of the airport frenzy, it was necessary to optimize the parking space to its maximum which was achieved with spans of more than 60 feet reducing the number of columns and making the whole safer to circulate. The limitation of construction effects on the daily life of the airport was also a prerequisite.

Photos